§ 6.8.1. [Sections four feet or greater in width.]  


Latest version.
  • For sections four feet or greater in width, the section shall comply with the construction standards for new streets, in accordance with the street's category as shown on the comprehensive plan. The base course must pass roll testing prior to paving. If a delay in paving is reasonably expected by the developer or the department, the base shall be primed with 0.25 gallon of R.C. 70 per square yard and cured for seven days before paving.

(Ord. of 2-24-2003(2))