§ 6.11.5. Construction methods.  


Latest version.
  • a.

    Curb and gutter shall be set true to line and grade, horizontal be field staked, and finished to the section shown on the plans. Along the project access improvements of a road which the city maintenance department has identified for resurfacing within one year of the new construction, the grade of the new gutter shall be placed one inch above the project access improvement pavement grade in areas where drainage will not be adversely affected.

    b.

    Line and grade shall be set by developer's engineer or surveyor on grades less than two percent and over 12 percent, and within 100 feet in both directions from all low points.

    c.

    One-half inch expansion joints or premolded bituminous expansion joint material shall be provided at all structures and radius points and at intervals not to exceed 250 feet in the remainder of the curb and gutter.

    d.

    Inferior workmanship or unprofessional construction methods resulting in unacceptable curb and gutter will be cause for rejection of the finished work.

    e.

    Disturbed areas along all curbing shall be backfilled, stabilized and grassed.

(Ord. of 2-24-2003(2))